Project Updates

Town of Ladysmith Wastewater Treatment Plant Upgrade - Headworks

May 2009         September 2009       January 2010       June 2010

June 2009        October 2009            February 2010     August 2010

July 2009          November 2009        March 2010

August 2009     December 2009        April 2010

 

Click on the images to see an enlarged view. Note: each image will open in a new window; to return to the project page, close the image window after viewing.

 

August 2010

West face view Pump floor view Blower room view


Back to Top

June 2010

 
Bin room Structural steel urethane coat - south face view  


Back to Top 

April 2010

 
Foul air scrubber installation Checker plate grating installation  


Back to Top 

March 2010

Concrete epoxy coating Bridge crane installation Finescreen installation
Pump discharge piping installation Grit classifier / washer installation MCC wiring


Back to Top 

February 2010

Rock trap formwork Parshall flume pour Q-deck installation
MCC cabinet installation Pipe chase construction

Bypass / overflow piping tie-in

Grit pump installation Back stabilization Slide gate grouting


Back to Top 

January 2010

Pump station suspended slab poured Structural steel erection Pump station bypass / overflow piping
Bin room and MCC room block wall construction Influent sanitary sewer installation Valve chamber piping


Back to Top 

December 2009

Pump station wall formation Fine screen slide gates installed Pump station suspended slab hatch formation


Back to Top 

November 2009

PR1 and PR2 slab on grade rebar PR1 and PR2 slab poured Upper row soil anchor extension
   
PR1 wall formation    


Back to Top 

October 2009

Fine screen and grit area channel and wall formation Fine screen, grit area channel and wall formation, pump station wall formation PR1 and PR2 chamber foundation


Back to Top 

September 2009

Grit chamber formation 11.50m level suspended slab rebar 11.50m level suspended slab poured


Back to Top 

August 2009

Blower room walls poured Pump station excavation Pump station foundation
   
Pump station slab rebar    


Back to Top 

July 2009

Blower room slab foundation Blower room slab pour Blower room wall formation
 
Upper row soil anchor drilling Upper row soil anchor drilling  


Back to Top 

June 2009

Middle row soil anchor drilling Lower row soil anchor wall penetrations Lean-mix foundation backfill
   
Middle row soil anchor drilling    


Back to Top 

May 2009

Bank excavation Erosion protection rip-rap wall placed at shore Lower row soil anchor drilling
 

Footing foundation

Seaside wall formation

 