October 2007
September 2007
August 2007
 |
|
October 2007 |
 |
 |
 |
|
Existing 250mm diameter Cast Iron watermain exposed, Oct. 1 |
Tees and gate valves assembled, Oct. 1 |
Putting up trusses, Oct. 1 |
 |
 |
 |
|
Ductile Iron pipes on site, Oct. 2 |
Megalugs for ductile iron pipes, Oct. 2 |
Concrete thrust block against tee, Oct. 2 |
 |
 |
 |
|
Megalugs installed, Oct. 2 |
Valve boxes are in with cold-mix over backfill, Oct. 2 |
Trench opened for dual watermain installation across road,
Oct. 3 |
 |
 |
 |
|
Roof trusses up, Oct. 3 |
Roof trusses up, Oct. 3 |
Ductile iron pipe installation, Oct. 3 |
 |
 |
 |
|
Ductile iron pipe with bedding, Oct. 3 |
Plywood and fascia on roof, Oct. 5 |
Electrical conduit installation across road, Oct. 9 |
 |
 |
 |
|
Roof membrane installation in progress, Oct. 11 |
Installation of antenna, Oct. 11 |
Drilling from outside of MH for sewer tie-in, Oct. 15 |
 |
|
|
|
Soffit is in, Oct. 15 |
|
|
|
|
|
|
|

September 2007 |
 |
 |
 |
|
Footing formwork up, Sept. 7 |
Steel work in footing, Sept. 7 |
Concrete in footing, Sept. 11 |
 |
 |
 |
|
Formwork stripped, inlet and outlet piping in, Sept. 13 |
Placing geofoam, Sept 16 |
Steelwork and floor drains in slab, ready for concrete pour,
Sept. 17 |
 |
 |
 |
|
Concrete pour in slab, Sept. 18 |
Concrete slab poured; ready for masonry wall Sept. 21 |
Masonry wall in progress
Sept. 25 |
 |
 |
 |
|
Door frame is in, Sept 25 |
Masonry wall is up, Sept 27 |
Inside of building, Sept. 27 |
 |
|
|
|
Trusses on site, Sept. 27 |
|
|
|
|
|
|
|

Back to Top |
|
August 2007 |
|
|
|