Project Update

Revelstoke WWTP - New Headworks Screening Building

Click on the images to see an enlarged view.

Note: each image will open in a new window; to return to the project page, close the image window after viewing.

December 2008
New Headworks building with concrete ramp,

Dec 3

Inside of building - discharge pipes and grating, Dec 3 Channel upstream level sensor, Dec 3
Screen with cover open,

Dec 3   

 Auger brush inside washer compactor,Dec 3 Spare parts,

Dec 3   

 
Local controller,

Dec 3   

Fan control drive,

Dec 3

 

Back to top     

November 2008
Screen, washer compactor c/w discharge pipe, Nov 4       6mm perforated plates,

Nov 4

Screen and washer compactor installed,

Nov 4   

Screen and washer compactor control panel, Nov 4        HVAC duct installed,

Nov 12

Brick facing installed on new building, Nov 17   

Back to top     

October 2008
New manhole formed,

Oct 3

Rebars in roof lab, Oct 3 Concrete pour in roof slab, Oct 6
Washer compactor on site, Oct 21 Outside of the new and exisitng building, Oct 24 Light fixtures installed, Oct 24
Inside of building,

Oct 27   

     Magmeters installed,

Oct 24

Fine screen on site,

Oct 28   

Gate valves on forcemains, Oct 29   

     Installing screen,

Oct 29

Screen and wastewater compactor installed in channel, Oct 31   

Back to top     

September 2008
Insulation under floor slab, Sep 3 Old power pole being removed, Sep 5 Block wall in progress, Sep 18
Block wall in progress,  Sep 19 Forming for concrete ramp, Sep 19 Inlet forcemains underway, Sep 22
Forming roof slabs,

Sep 23

Metal Flashing,

Sep 25

Insulation outside block wall, Sep 30

Back to top     

July - August 2008
Forming foundation walls Rebar in foundation Concrete pour in foundation
 
Inlet stainless Steel Piping Prepare New Headworks Building site  

Back to top     