District of Squamish Boulevard Pump Station Replacement

The construction of a water pumping station (2-100 HP vertical turbine) and related appurtenances including the construction of a structural block building and metal clad roofing, and related mechanical and electrical appurtenances, valve chamber, 250 kW generator, pipe and site work, and decommissioning and demolition of the existing station.

January 2010           May 2010             

February 2010         June 2010               

March 2010              September 2010       

April 2010                December 2010       

 

Click on the images to see an enlarged view. Note: each image will open in a new window; to return to the project page, close the image window after viewing.
 


Back to Top 

October 2010

Completed standby power generator south of Pump Station. South building elevation (rear). Touch-screen control panel on MCC
 
MCC units. Completed Pump Station building.  


Back to Top 

September 2010

 
Old pump station is demolished. Pipe from adjacent Boulevard Reservoir to new pump station.  


Back to Top 

June 2010

Space left for additional pumps in the future. BC Hydro kiosk installed on new pad. Pumps complete.
   
Metal siding covers concrete block walls.    


Back to Top 

May 2010

 
Insulation in attic space. Pump set in place, ready for concrete base.  


Back to Top 

April 2010

Rigid insullation installed on exterior walls under metal siding. Drywall on ceiling. Waterproof membrane installed on block walls.
 
Waterproof membrane installed on block walls. Roof trusses installed on concrete block walls.  


Back to Top 

March 2010

Finished main floor slabs. Rebar and forms ready to cast main floor slab. Floor slabs for pipe channels cast.


Back to Top 

February 2010

 
Project Engineer and Contractor's Superintendant examine pipes on north wall. Open form work for north wall.  


Back to Top 

January 2010

Foundation footings. Sub-grade is filled with mass concrete, encasing live AC water main. Form for west side foundation footing.

Electrical ducts installed in concrete along west side of site.

Site excavation is started

Construction starts