Project Updates

District of Squamish Boulevard Pump
Station Replacement
The construction of a water
pumping station (2-100 HP vertical turbine) and related appurtenances
including the construction of a structural block building and metal clad
roofing, and related mechanical and electrical appurtenances, valve
chamber, 250 kW generator, pipe and site work, and decommissioning and
demolition of the existing station.
January 2010
May 2010
February 2010 June 2010
March 2010
September 2010
April 2010
December 2010
Click on the images to see an enlarged view.
Note: each
image will open in a new window; to return to the project page, close
the image window after viewing.

Back to Top
October 2010
 |
 |
 |
|
Completed standby power generator south of Pump Station. |
South building elevation (rear). |
Touch-screen control panel on MCC |
 |
 |
|
|
MCC units. |
Completed Pump Station building. |
|

Back to Top
September 2010
 |
 |
|
|
Old pump station is demolished. |
Pipe from adjacent Boulevard Reservoir to new pump station. |
|

Back to Top
June 2010
 |
 |
 |
|
Space left for additional pumps in the future. |
BC Hydro kiosk installed on new pad. |
Pumps complete. |
 |
|
|
|
Metal siding covers concrete block walls. |
|
|

Back to Top
May 2010
 |
 |
|
|
Insulation in attic space. |
Pump set in place, ready for concrete base. |
|

Back to Top
April 2010
 |
 |
 |
|
Rigid insullation installed on exterior walls under metal
siding. |
Drywall on ceiling. |
Waterproof membrane installed on block walls. |
 |
 |
|
|
Waterproof membrane installed on block walls. |
Roof trusses
installed on concrete block walls.
|
|

Back to Top
March 2010
 |
 |
 |
|
Finished main floor slabs. |
Rebar and forms ready to cast main floor slab. |
Floor slabs for pipe channels cast. |

Back to Top
February 2010
 |
 |
|
|
Project Engineer and Contractor's Superintendant examine pipes
on north wall. |
Open form work for north wall. |
|

Back to Top
January 2010

Back to Top
|