Projects -
Reservoirs

Some
of our Reservoir projects include:
 |
Kispiox Band Standpipe Water Storage Reservoir,
Kispiox, BC |
 |
 |
Mount Shannon Reservoir,
City of Chilliwack, BC |
 |
 |
Promontory Zone 3 Reservoir
Design Build Project,
City of Chilliwack, BC |
 |
 |
Establishment of High Zone Pressure
Zone,
District of 100 Mile House, BC |
 |
 |
Duncan Avenue Reservoir Expansion,
City of Penticton, BC |
 |
 |
Eagle Lake Water Storage Reservoir,
District of West Vancouver, BC |

Kispiox Band Standpipe Water Storage Reservoir

Due
to population growth in Kispiox, additional water storage was required
to enable the water supply system to meet the community’s current and
projected peak hour demands and to provide adequate storage for fire
fighting purposes.
Dayton & Knight Ltd. completed a feasibility study investigating various
options for providing the required storage. The options considered
included standpipe reservoirs at various locations and conventional
reservoirs located on elevated locations outside the village. A second
standpipe reservoir located in the village above the new subdivision
area was determined to be the most cost effective solution to meet the
community’s current and future needs.
Dayton & Knight Ltd. completed the design and construction
administration for the second standpipe reservoir. The project included
construction of a 30m tall bolted steel standpipe tank, a control valve
chamber, watermain connecting to the distribution system, an access road
and miscellaneous site works. Modifications were made to the piping in
the existing reservoir to enable
mixing of the stored water and a control valve chamber was installed to
enable control over the filling of both reservoirs.
The water treatment plant operation is controlled based on the water
levels in the reservoirs. The water level in both reservoirs is measured
using ultrasonic sensors and the information sent via radio link to the
water treatment plant. An uninterruptible power supply (UPS) was
installed at the existing reservoir to power the level sensor and radio
equipment to ensure level information is available in the event of a
power outage. With the water treatment plant having auxiliary power, the
water supply system is fully functional during a power outage.

Mount Shannon Reservoir, City of Chilliwack, BC

Dayton & Knight
Ltd. designed and administered a contract for the construction of a 20
million litre water reservoir.
Construction occurred in two phases:
a) Removal of existing lining and construction of new lining, columns
and walls.
b) Roof construction.
Between the two
phases, the reservoir was used by the City to provide water for the
summer peak draws. Excavation costs were minimized by constructing
the walls to approximately follow the contours of the original reservoir
basin. The reservoir has a central wall which will allow cleaning
of one half with the other half in service.

Promontory Zone 3 Reservoir
Design Build Project,
City of Chilliwack, BC

Dayton & Knight Ltd.
in association with Tri-River Enterprises Ltd. designed and built
the 5.4 million litre (1.2 MG) reservoir storage facility.
The
project consisted of a supply main and storm sewer and two 2.7 ML
(0.6 MG) reinforced concrete reservoirs on a steep site. The
tight design and construction schedule requirements were met and the
unique design was less than the next bid received by the City.

Establishment of High Zone Pressure
Zone, District of 100 Mile House, BC
 A second and higher distribution
pressure zone was established by the District to complement the
lower pressure zone. The work included the construction of a
450 cubic metre water storage reservoir (pictured), a
booster pumping station, a pressure reducing valve station, and
1,300 m of 200 mm diameter watermain and appurtenances between the
booster pumping station and the reservoir.
The
partially buried reservoir is 12 m in diameter by 3.8 m deep, and
is constructed of reinforced cast-in-place concrete. The booster
pumping station has two forty horsepower split case pumps and
surge control equipment to supply 1.80 cubic metres per
second. Provision is made for the future addition of a third
pump and an increase in the pump impeller diameters to bring the
pumping capacity to 3.10 cubic metres per second.

Duncan Avenue Reservoir Expansion, City of Penticton, BC
Dayton & Knight designed the upgrading and
expansion to the existing Duncan Avenue reservoir in the City of
Penticton. The old reservoir was constructed circa 1911/1912
with a capacity of approximately 3,200 cubic metres (0.7
mg). The reservoir was open to atmosphere and had a water
depth of 3.5 m. By the early 1980's the reservoir was surrounded
by residential development and was falling short of meeting the
City's water distribution balancing needs.
The
expansion included the addition of perimeter walls 2 m in height,
resurfacing the entire concrete liner with new concrete,
constructing a column supported roof and installing miscellaneous
mechanical piping. The work increased the reservoir capacity
to 5,500 cubic metres (1.2 mg). Construction required 850
cubic metres of reinforced concrete.

Eagle Lake Water Storage Reservoir,
District of West Vancouver, BC
 The Eagle Lake
water storage reservoir serves the west end of West
Vancouver.
The two dams in the lake were raised 4.0 to 5.0 metres
and a new concrete spillway and outlet works were constructed.
Raising
the dams increased the usable storage in the lake to 280 million
gallons and increased the dam heights to approximately 10 metres.
Dayton & Knight Ltd. designed and supervised construction of
the modifications.

For more information about Dayton & Knight Ltd.'s
capabilities and experience, please contact:
John
Boyle
(jboyle@dayton-knight.com)

Back to Top |